Borough Hall Construction Update

The steel frame work has been completed. You will now see the metal decks for the first and second floors as well as the roof being installed. Then slabs will go on top of the decks with concrete poured on top of those. The mason will come to put in the concrete foundation which will go from the ground to the first floor around the perimeter of the building. If all goes well, this will take 2-3 weeks. At this point, with rare exceptions for heavy equipment, Downer has been re-opened for vehicles.Also, tomorrow, 7/4, the parking lot at DPW will undergo repairs
from 12:00-4:00 so please don’t plan on using that lot until Friday evening. Please call Councilman White with any questions or comments.