Weekly Beach Replenishment Update – 12/13

Unfortunately, there has been no progress this last week. As mentioned in the last post, a cable snapped on the starboard side of
the barge. This part has been ordered and arrived yesterday. If all goes well, the barge should return by Saturday or Sunday and even with the high winds we are experiencing today the swells are an acceptable 5.5 feet and going down over the next few days. This is good news.The two crossovers at Downer and Princeton are not completed and both have exceeded the allowable 14 days. Weeks Marine, the contractor, is awaiting revised plans for Princeton Ave. from the Army Corps of Engineers. These should be forthcoming shortly. Please feel free to call with any comments or questions. Councilman White – 732-606-6988