Steel Revetment Update – 9/4/14

The steel contractor EIC has started to work 12 hour days.  They will be driving steel from 6 AM to 6 PM daily, at 220 feet a day.  Currently there is only one machine working in Mantoloking and it is located in the area of Princeton.  That machine is going to continue approximately 100 feet to the south of Princeton and then be relocated to the north where the 2nd machine was located.  The contractor is projecting to be in the area of Lyman by the 3rd week of September, at which time they will also receive delivers of the rocks needed to tie into the already existing revetment.  After work is finished at Lyman the machine willmove back to the area of Princeton and continue south into Brick. The second phase of the project, the installation of caps has begun and once the contractor reaches 1000 feet he will start to place the scour apron.