New Jersey Natural Gas Pipeline Project

Please see below the schedule of events for the next two weeks as we begin the gas pipeline project with NJNG.

Week of 11/6/17
Carson Corp. (drilling contractor) will be performing utility test holes on Arnold Street. Carson Corporation will be installing road construction warning signs per approved traffic control plans.

Week of 11/13/17
Carson Corporation will begin mobilizing drilling equipment to NJAW yard on Bay Ave./Arnold St. and begin setting up road closure of Arnold Street.

This job is expected to take 2-3 months and there will be no interruption of service. All driveways on Arnold and Bay Avenue will be accessible. Please contact Councilman White (732) 606-6988 if you have any questions. Thank you.